Project Description

McCrossin completed electrical work for the installation of a crusher and conveyor system in the Graymont mine. We were responsible for the mechanical installation of the 102 Screen Tower, including the equipment housed inside the tower like the Metso Screen, McLanahan Tertiary Crusher, IAC dust collector, dust collector fan, ducts, stack, air compressor, and the installation of the BEC-196 Conveyor. We also performed the structural steel services, grating, walkways, handrails, kick plates, chutes, etc.

Project Details

Job Name: Graymont Mine Conveyor Electric

Job Location: Graymont, Pennsylvania

Start Date: March 1, 2012

Completion Date: February 1, 2013